C-SRNWP Programme
Third Quarterly Report for 2013 (July - September 2013)
Prepared by: Gergely Bölöni, C-SRNWP PM
Hungarian Meteorological Service
1024 Budapest, Kitaibel Pal utca 1., Hungary
For submission to: EIG EUMETNET Secretariat
Summary:
Action required: For information and comment
Distribution: Public
Reference |
Date |
Author(s) |
Content |
|
October 30, 2013 |
Gergely Bölöni |
First version |
The main activity of the C-SRNWP programme is the scientific and technical (operational)
coordination between the five LAM Consortia in Europe (ALADIN, COSMO, HIRLAM,
LACE and Met Office). The coordination is ensured by the eight Expert Teams
(data assimilation and use of observations; diagnostics, validation and
verification; dynamics and lateral boundary coupling; link with applications;
physical parameterization: upper air; predictability and EPS; surface and soil
processes: model and data assimilation; system aspects) established in 2008 and
through the regular correspondence, including the annual meeting, between the
members of the SRNWP Advisory Expert Team Committee (previously called Advisory
Committee), which consists of the consortia heads and the Expert Team chairs. Standing
for the success of the EUMETNET programmatic targets, coordination with other
Forecasting (SRNWP-EPS, Nowcasting) and Observation
(EUCOS, OPERA) Projects/Activities is done. During the third quarter of 2013
the following coordination efforts have been made.
Participation at the Obs-SET meeting
Input information was prepared for the annual Obs-SET meeting by the C-SRNWP PM on behalf of the SRNWP
community (see the Q2 report). The C-SRNWP PM also attended the Obs-SET meeting and presented this input information (SRNWP
activities regarding the assimilation of BUFR radisonds,
EUCOS monitoring standards, observing network design from SRNWP point of view,
status of OPERA radar volume data handling for NWP purposes). A presentation on
the current status of the C-SRNWP project has also been given at the meeting.
Presentation on the
status of the C-SRNWP Project at the COSMO General Meeting
The current status of the project has been
presented by the C-SRNWP PM at the COSMO General meeting. The participation at
the meeting also fostered progress in two important coordination subjects: a)
the COSMO community suggested to open the access of the SRNWP data pool to
universities/academia, b) following the discussions, the C-SRNWP PM learned a
lot about the cooperation between the NWP and academic communities involved
with the COSMO model.
SRNWP data pool for
universities/academia
The SRNWP data pool is currently accessible for
C-SRNWP project members. The data included in the pool helps the validation of
soil models and soil-atmosphere interfaces in NWP models (the data are
accessible with a delay of half year to prevent their use in operational
analysis and forcasting). It is a general view of the
SRNWP community that providing the SRNWP data pool to universities would foster
the development of NWP soil or atmospheric models at universities, offering an
additional manpower available at NMSs. The C-SRNWP PM prepared a proposal for
the next STAC meeting (October 2013) promoting the access to universities.
Questionnaire on
promoting European NWP models for education
The webex meeting
held in this subject in June 2013 (with the participation of the EUMETCAL PM, Forecasting
PM, OpenIFS team) concluded that information is needed from the SRNWP
consortia about their expectations with respect to cooperation with
universities/academia regarding NWP education and research. As a consequence, a
questionnaire has been prepared by the C-SRNWP PM (with the involvement of the
EUMECAL PM and the Forecasting PM) and sent to the SRNWP consortia (ALADIN,
COSMO, HIRLAM, LACE, UKMO) leaders.
Preparation of the
EWGLAM/SRNWP meeting
The preparation of the scientific programme for the EWGLAM/SRNWP meeting (30 September – 3
October) has been started in July and finished a few weeks before the meeting.
The programme was drafted by the C-SRNWP PM with the
help of the Expert Team chairs (Data Assimilation, EPS, Link with Applications,
Verification). Preparations included the overview of the model-to-model
adaptors developed in the frame of the SRNWP-I Programme.
This has been done by the former SRNWP-I Programme
Manager and the C-SRNWP PM with the help of the System Expert Team. The
relevant ET members provided information about the “Annual adaptor testing”
(agreed in the document “SRNWP Interoperability:
Adaptor software maintenance
regime“) to be presented at the EWGLAM/SRNWP meeting.
Communication with
ECMWF regarding the extension of IFS EPS boundary conditions for very high
resolution EPS systems
A planning of the ALADIN/LACE contribution to
the high resolution IFS LBC tests has been done for October 2013 (a Hungarian
and an Austrian scientist will work on this subject in Vienna). ECMWF kindly
offered to ensure a venue for the scientific workshop discussing the results of
all consortia (ALADIN/LACE, COSMO, HIRLAM) at the beginning
of December. A preliminary agenda has been drafted by the EPS Expert Team chair
and the C-SRNWP PM, which was sent to ECMWF for refinement.
|
Explanatory notes: |
R1: OMSZ has paid only the half
of its 2013 EUMETNET contribution
and consequently only the first installment
has been paid by EUMETNET to OMSZ for C-SRNWP. The second installment will be paid by EMN to OMSZ for C-SRNWP at reception of
OMSZ payment of 2013 Contributions
by the end of the year. |
R2: The 2013 overspending (381€)
is covered from last year's surplus. This change has been done under the
right of the 2013 financial
delegation and with the approval of the FPM and ED EUMETNET. |
None to report.